Gjuterikvalitetssystem: PPAP, APQP, FAI, NDT & IATF 16949

DE 18 ELEMENTEN I PPAP NIVÅ 3 FÖR GJUTTERIER

When qualifying a foundry for high-volume serial production (automotive engine blocks, heavy equipment transmissions, or hydraulic manifolds), STALFE requires a complete PPAP Level 3 Dossier (QAI-001). Below is the exact operational requirement for each of the 18 mandatory PPAP elements.

PPAP-elementnummer och namn Obligatoriskt tekniskt innehåll och dokumentation krävs STALFE Acceptanskriterier (noll avvikelse)
1. Designa poster & CAD-modeller Approved 2D engineering drawings (PDF) and 3D CAD models (STEP) annotated with ISO 8062 CT8 tolerances and GD&T datums (A-B-C). Exakt ritningsrevisionsbrev stämplat och verifierat mot kundens inköpsorder.
2. Tekniska förändringsdokument Any documented engineering change notes (ECN), deviation authorizations, or concessions agreed between STALFE and OEM buyer. Helt signerad av kundens chefsingenjör innan FAI-gjutning.
3. Kundens tekniska godkännande Written sign-off from STALFE engineering approving the pattern layout, gating/risering simulation (MAGMASOFT), and parting line location. MAGMASOFT-simulering måste visa noll centrumlinjekrympning hot spots inuti kritiska bossar.
4. Design FMEA (DFMEA) Systematic analysis of potential part design failures under mechanical fatigue, hydrostatic pressure (500 bar), or thermal shock. Risk Priority Number (RPN) must be < 100 for all critical operating modes.
5. Process Flow Diagrams (PFD) End-to-end visuell kartläggning av gjuteriprocessen: skrotladdning -> elektrisk induktionssmältning -> OES -> gjutning -> shakeout -> kulblästring -> CNC-svarvning -> CMM -> NDT -> förpackning. Måste inkludera alla verifieringsportar för inkommande, pågående och slutlig inspektion.
6. Process FMEA (PFMEA) Rigorous analysis of manufacturing failure risks (e.g., core shift during pouring, damp sand causing gas porosity, or OES drift). Must incorporate automated Poka-Yoke checks (e.g., core setting alignment pins and automated radiation monitors).
7. Control Plan (CP) The master operational inspection schedule specifying check frequency, gauge type, and corrective action (CAPA) for every process step. Must mandate 100% CMM sampling on first 5 parts and hourly green sand moisture checks (3.0 - 3.5%).
8. Measurement System Analysis (MSA) Statistical Gage R&R-studier utförda på alla CMM, borrmikrometrar och bromsok som används för att kontrollera kritiska ritningsdimensioner. Gage Repeatability & Reproducibility (Gage R&R) percentage must be ≤ 10.0%.
9. Dimensional Results (CMM Layout) Complete 100% dimensional inspection reports on 5 to 6 consecutive First Article Inspection (FAI) castings measured across all CAD features. All dimensions must fall within ISO 8062 CT8-CT10 raw casting or H7 machined tolerance bands.
10. Material- och metallurgiska rapporter Certified laboratory test reports: OES chemical composition (% C, Si, Mg, Cr, Mo), tensile/yield tests from cast bars, and nodularity image analysis (ISO 945-1). Must prove Nodularity ≥ 85% (ductile iron) and tensile yield properties conforming to EN 1561 / EN 1563 (EN 10204 Type 3.1 signed by independent QA).